Resurfacing Works May 2017
Resurfacing Works May 2017.
Information received by Northamptonshire Highways.
“Whilst every effort will be made to keep to this schedule it must be recognised that all resurfacing works are weather dependent and changes to the timetable may be necessary as works proceed.
Sunday 14th and Monday 15th May – 1200 – 0600: Harlestone Road
From Spencer Bridge Road to Weedon Road
Tuesday 16th to Thursday 18th May: 1900 – 0600: Weedon Road/ St James Road, Westbound
From Bowden Road heading west to Spencer Bridge Road
Friday 19th and Saturday 20th May: 1900 – 0600: Weedon Road St James Road, East Bound
From Spencer Bridge Road heading east to Bowden Road
Sunday 21st May: 1200 – 0600: Spencer Bridge Road Northbound
From outside 55 Weedon Road, turn left onto Spencer Bridge Road and resurface to and including the Harlestone Road crossroads.
Monday 22nd May: 1900 – 0600: Spencer Bridge Road Southbound
From Harlestone Road Crossroads to Weedon Road”